Schemes : Centrally Sponsored Schemes : Pradhan Mantri Gram Sadak Yojana (PMGSY)

2.7 Pradhan Mantri Gram Sadak Yojana (PMGSY)

Pl. click here for GOI Guidelines
Pl. click here for all G.Os

The Government of India launched PMGSY on 25th December 2000 to provide all weather roads to all rural habitations with population more than 1000 in the first phase and to all habitations with population between 500 and 1000 in the second phase. This is a 100% Centrally assisted scheme. In the first three Phases, Rural Development and Panchayat Raj Department has taken up 3370.97 Kms at an estimated cost of Rs. 434.08 Crores. So far 3299.95 Km road works have been completed with an expenditure of Rs. 385.21 Crores. Under Phase IV, 820.46 Km road works at an estimated cost of Rs. 117.27 crores were entrusted to Highways Department for implementation. Rural Development and Panchayat Raj Department is implementing the Scheme under Phase V and road works to a length of 849.25 Km at an estimated cost of Rs. 182.05 Crores have been taken up. 405.91 Km road works have been completed with an expenditure of Rs. 74.96 crores so far.

Thalaiyuthu - Manoor Road , Dindigul District


Pl. click here for Photo Gallery

Table 2.7.1
Pradhan Mantri Gram Sadak Yojana – (PMGSY)

Sl. No.

Phase

Financial
Allocation
(Rs. in crores)

Physical
Allocation

Nos.

Km.

1

Phase 1

153.49

866

1,448.47

2

Phase 2

115.81

450

808.58

3

Phase 3

164.78

498

1,113.92

4

Phase 4

117.27

412

820.46

5

Phase 5

182.05

379

849.25

 

Total

733.40

2605

5,040.68

Bharat Nirman was launched by Government of India in April 2005 as a time bound business plan of Government of India for building rural infrastructure in the areas of irrigation, roads, housing, water supply, electrification and telecommunication connectivity.

Under the roads component of Bharat Nirman:

         Every habitation of over 1000 population and above (and above 500 in hilly and tribal areas) would be provided all-weather road connectivity.

         ‘Through routes’ in the Core Network connecting farm to market are to be upgraded.

Funds under PMGSY (for new connectivity and Upgradation) and from State Government (for renewal) are being used to achieve the targets of the road components of Bharat Nirman.

Status of connectivity of habitations is determined as per the Core Network. Core Network was revised in December 2007 and as per the revised core network status of connectivity is as follows:

Table 2.7.2
Status of Connectivity as per the Revised Core Network

 

1000+

500-
999

250-
499

Less
Than
250

Total

Total No. of habitations

10,783

16,513

17,104

18,519

62,919

Total no. connected habitations

10,764

16,234

16,574

17,439

61,011

Balance unconnected habitations

19

279

530

1,080

1,908


19 uncovered habitations (96 eligible, 77 covered, leaving a balance of 19 uncovered) will be covered in the forthcoming phases. The detailed project reports (DPRs) for the 19 habitations are being prepared under Bharat Nirman Phase II and will be sent to MoRD, GOI shortly.

Table 2.7.3
Length Coverage (Upgradation and Renewal) under Bharat Nirman

SL. No

Target
(2005-2009)

Cumulative achievement up to April’ 2008

Cumulative achievement in %

1

11,115 Km

6,343.50

57.10


Phase wise achievement is as follows:

Table 2.7.4
Progress under Bharat Nirman

Category

Target
Length
(in Km)

Achievement
(in Km)

Balance

Source of Funds

 

PMGSY
Phase

Length
(in Km)

Upgradation

6,670

II

27.2

5348.2

PMGSY

III

267.9

IV

642.9

V

383.8

Total

1,321.8

Renewal

4,445

5021.70

0

State
Govt.
(12th Finance
Comm. and CRIDP)

Total

11,115

6343.50

5342.7

 


Out of the proposals (DPR) for 1700 Km cleared by GoI, 1328 Kms have been completed till date. The works for the remaining 372 Kms of roads will be completed by June’ 2008.
A proposal from Rural Development and Panchayat Raj Department to a length of 797 Kms to a tune of Rs. 195 crores and a proposal from Highways Department to a length of 1,286 Kms to a tune of Rs. 232 crores totally, the proposal of 2,083 Kms to a tune of Rs. 427 crores have been cleared by MoRD during May’ 2008 as PMGSY Phase VI (or Bharat Nirman Phase I) scheme. These works will be implemented shortly.